Otis: Made to Move — Once the Camera Roll

9 min read4 days ago

--

How two television news reports in Shanghai exposed questions about project management, contractor oversight, and corporate accountability at one of the world’s largest elevator companies.

Otis is one of the world’s most recognizable elevator brands. Its corporate slogan, “Made to Move You,” reflects a commitment to mobility and connecting people.

But in our residential community in Shanghai, China, the experience of replacing aging elevators raised a rather uncomfortable question:

Why did it take TV journalists to get an elevator modernization project moving?

In October 2026, our community’s Otis elevator modernization project became the subject of two Shanghai TV reports, broadcast on October 17 and October 25.

I am a resident of the community and have been closely following the project, communicating with Otis representatives, documenting construction progress, and collecting feedback from other residents.

What I witnessed was a striking contrast between the project’s management before and after media intervention.

Before the journalists became involved, residents struggled with unclear schedules, inconsistent communication, installation delays, and problems affecting newly commissioned elevators.

After media attention, several elevators progressed through inspection and returned to service within a relatively short period.

The contrast does not prove that every previous delay was avoidable. But it raises serious questions about how Otis manages residential modernization projects and responds to customers.

1. An Elevator Modernization Project That Residents Could Barely Track

Our residential community in Shanghai consists of multiple buildings, including high-rise residential towers.

In 2026, the community selected Otis to replace its aging elevators with Gen3 MOD modernization products.

The contract price was approximately RMB 180,000 per elevator, according to the project documents available to me.

Residents reasonably expected a professionally coordinated installation process from an internationally recognized manufacturer.

Instead, we encountered a recurring problem: a lack of transparent and reliable project information.

Construction information boards at some sites contained no meaningful updated schedules. Residents often had difficulty determining when installation would finish, when inspections would take place, and when elevators would finally return to service.

Press enter or click to view image in full size
All the project timeline on the Construction board is blank

This was particularly frustrating because the elevator replacements affected residents’ daily lives.

For people living on upper floors, especially elderly residents and people with limited mobility, a prolonged elevator outage is much more than an inconvenience.

It affects their ability to leave home, attend medical appointments, carry groceries, and maintain ordinary routines.

Yet basic questions about project progress were often difficult to answer.

A construction schedule should not be something residents have to investigate for themselves.

2. The Problems Went Beyond Construction Delays

Delays were not our only concern.

Some newly installed elevators experienced operational problems after being put into service.

In one building, an elevator that had recently resumed operation was taken out of service again. In another, residents reported repeated interruptions and reliability concerns.

These incidents raised questions about commissioning, troubleshooting, and the handover process.

To be clear, an operational interruption does not automatically establish a manufacturing defect or a violation of safety standards.

Elevator systems are complex, and newly installed equipment may require adjustments. However, repeated problems immediately after commissioning deserve careful investigation and clear explanations.

Residents should be able to understand whether an interruption was caused by installation work, equipment defects, control-system settings, external conditions, or other factors.

Without transparent technical explanations, confidence in the project inevitably deteriorates.

3. October 17: When Television Journalists Became Involved

On October 17, 2026, Shanghai Media Group (SMG) broadcast a report about the elevator modernization problems in our community.

Watch the October 17 television report on YouTube

The involvement of journalists marked an important turning point.

According to information I received during the project, the television station contacted relevant authorities regarding the inspection arrangements.

Four elevators were reportedly submitted for inspection on October 15, followed by on-site inspections on October 16.

An expedited inspection arrangement was facilitated after the television station contacted the relevant authorities.

This detail is important.

The accelerated inspection process cannot simply be credited to Otis. Journalists and inspection authorities played significant roles.

Nevertheless, the events demonstrated something important about the project’s coordination.

Processes that residents had struggled to understand suddenly became more visible and began producing results.

The question is not whether inspections should have been rushed or safety requirements relaxed. They should not.

The question is why better coordination and clearer communication had not been achieved through ordinary project management.

Why did external intervention become necessary for a routine residential elevator modernization project?

4. After the Cameras Arrived, Things Started Moving

Following the journalists’ involvement, several elevators progressed through inspection and were returned to service around October 22.

From a resident’s perspective, the contrast was remarkable.

Before media intervention, residents had difficulty obtaining reliable progress updates and understanding the reasons for delays.

Afterward, tangible progress became visible within days.

Of course, correlation does not necessarily establish causation.

Some work may already have been nearing completion. Inspection schedules depend on regulatory authorities, and installation contractors may have been completing final adjustments.

But this does not eliminate the management questions.

If several elevators were sufficiently ready to progress through inspection and commissioning within such a short period, what prevented the project from being coordinated more effectively beforehand?

Was there a shortage of installation personnel?

Were project milestones inadequately monitored?

Were inspection submissions delayed?

Was communication between Otis, its installation teams, property management, and the inspection authorities insufficient?

Or were residents’ concerns simply not receiving adequate management attention?

These are questions that Otis should be able to answer with project records, schedules, and documented explanations.

5. October 25: The Follow-Up Television Report

On October 25, Shanghai Media Group (SMG) broadcast a follow-up report concerning the project.

Watch the October 25 follow-up report on YouTube

The second report provides an opportunity to examine what changed after the initial media exposure.

For residents, the meaningful indicators were not public-relations statements or verbal assurances.

They were practical outcomes: elevators passing the required inspections, returning to service, remaining operational, and outstanding problems being addressed.

The important question is whether the progress following the first report reflected a sustainable improvement in project management or merely a temporary response to external attention.

A successful elevator modernization project should not be measured solely by the date an elevator is handed over.

Its reliability during the weeks and months following commissioning matters just as much.

6. Why Blaming Installation Contractors Is Not Enough

One possible explanation for the problems is that elevator installation work is frequently performed by specialized installation teams or subcontractors.

Indeed, different installation teams were reportedly involved in different buildings within our community.

Some teams appeared to progress differently from others.

However, the presence of subcontractors does not remove the need for effective overall project management.

The precise contractual responsibilities depend on the agreements among the manufacturer, installation companies, and project purchaser.

But regardless of the contractual structure, a company presenting itself to customers as the provider of an integrated elevator modernization solution should be able to explain how it supervises delivery.

Get Tony Q.’s stories in your inbox

Join Medium for free to get updates from this writer.

Consider the following questions:

  • Who establishes and maintains the overall construction schedule?
  • Who verifies that installation contractors have sufficient personnel and resources?
  • Who monitors delays and coordinates corrective action?
  • Who oversees commissioning and readiness for inspection?
  • Who communicates changes to residents and property management?
  • Who takes responsibility when multiple buildings encounter similar coordination problems?

These are management responsibilities, not merely technical installation tasks.

Even if an individual delay originates with an installation contractor, the effectiveness of the overall management system determines whether the problem is identified early, communicated transparently, and resolved efficiently.

Subcontracting the installation work should not mean subcontracting accountability.

This is why I believe our community’s experience deserves attention beyond the performance of individual installation teams.

The larger issue is the effectiveness of Otis’s project delivery and contractor oversight arrangements.

7. My Experience Escalating Concerns to Otis Management

My own attempts to communicate with Otis further reinforced these concerns.

On October 13, a planned meeting with the project manager was cancelled.

Chunjun Wu, the project manager, said he cannot answer my questions and cancel the meeting directly.

I subsequently sought written clarification regarding the project’s progress and outstanding issues.

Obtaining timely and substantive responses proved difficult.

Eventually, I escalated my concerns through email correspondence that copied President of Otis China, Sally Loh.

Following this escalation, I received further communication from company representatives.

I cannot independently establish that copying senior management caused the response, or determine what internal discussions occurred.

But the sequence left me with another question.

Why should an ordinary resident need to escalate a relatively small residential project to senior corporate leadership to obtain meaningful engagement?

A mature project management organization should have effective escalation procedures at the local level.

Project managers should be empowered to explain delays, coordinate resources, resolve disputes, and communicate corrective actions.

Senior executives should not need to become involved in routine construction scheduling problems.

When communication improves only after a customer escalates concerns to higher levels, it is reasonable to examine whether the ordinary customer-service and project-management processes are functioning as intended.

8. Technical Capability Is Not the Same as Management Capability

I do not believe our experience proves that Otis is incapable of manufacturing reliable elevators.

Otis has a long engineering history and operates in a technically demanding industry.

Elevator technology, manufacturing quality, installation workmanship, commissioning, maintenance, and project management are different aspects of the overall customer experience.

A company may have strong engineering capabilities while still struggling with local project execution.

Our community’s experience illustrates why this distinction matters.

The problems we encountered were not limited to the equipment itself.

They involved scheduling, transparency, coordination, communication, and accountability.

These are management issues.

And unlike certain technical challenges, many management problems do not require breakthroughs in engineering to solve.

They require clearly assigned responsibilities, realistic schedules, adequate resources, and effective supervision.

The progress observed around the media intervention suggests that improved coordination was possible.

It does not establish precisely why that coordination was not achieved earlier.

But it makes the question worth asking.

9. What Otis Should Explain

I believe Otis could address many of these concerns by providing straightforward answers supported by project documentation.

For example:

Project scheduling: What were the original completion dates for each elevator, and why did actual delivery differ from those dates?

Contractor management: How did Otis monitor installation progress, staffing levels, and the performance of the installation teams?

Inspection coordination: When was each elevator ready for inspection, when was each application submitted, and what caused any gap between those milestones?

Commissioning and reliability: What caused the operational problems reported after certain elevators were returned to service, and what corrective actions were taken?

Customer communication: Why were residents unable to obtain reliable, regularly updated construction schedules?

Escalation procedures: What internal processes existed to resolve persistent project issues before journalists or senior corporate leadership became involved?

These are reasonable questions about the delivery of a contracted service.

Answering them would help distinguish unavoidable technical or regulatory delays from problems caused by inadequate coordination.

It would also help residents understand what improvements, if any, Otis has implemented to prevent similar experiences elsewhere.

10. Made to Move — Once the Cameras Roll?

Otis’s corporate slogan is “Made to Move You.”

It is a powerful promise for a company whose products are essential to the daily movement of millions of people.

But our experience in Shanghai revealed an uncomfortable gap between the promise of mobility and the reality of project delivery.

For weeks, residents struggled with uncertain schedules, incomplete information, and unresolved concerns.

Then television journalists became involved. Within a relatively short period, inspections progressed and several elevators returned to service.

I do not claim that television coverage alone caused every improvement, or that all previous delays were deliberate or avoidable.

But the contrast deserves an explanation.

If the project could progress more effectively under external scrutiny, what prevented the same level of coordination, urgency, and transparency from being applied earlier?

Why did residents have to depend on journalists to help obtain information and attention that should have been available through normal project management?

And what does this experience reveal about the relationship between a global elevator brand and the local teams responsible for delivering its promises?

A company’s true standard of service is not how quickly it responds when television cameras arrive. It is how consistently it serves customers when nobody is watching.

Otis says it is “Made to Move You.”

For residents of our community, the experience sometimes felt closer to:

Made to Move — Once the Cameras Roll.

References

Television coverage

  1. Shanghai television, October 17, 2026. Initial report concerning the residential elevator modernization project.
  2. Shanghai television, October 25, 2026. Follow-up report concerning the project.

Project documentation and firsthand observations

  1. Elevator modernization contract and related project materials held by the author.
  2. Construction information boards, installation schedules, and dated site observations.
  3. Correspondence with Otis project representatives and management.
  4. Resident feedback and records of reported operational interruptions.

Author’s disclosure: I am a resident of the Shanghai community discussed in this article and have personally followed the elevator modernization project. This article combines my firsthand observations, correspondence, information provided by other residents, and references to television coverage. Management-related assessments represent my interpretation of the documented events. Some technical and contractual details remain subject to further verification, and the parties involved may have additional explanations.

--

--